Installation of Renewable Energy Generation Capacities
AB “Linas” is implementing the project “Installation of Renewable Energy Generation Capacities” partially funded by the European Union funds. The goal of the project is to increase the share of renewable energy resources in final energy consumption.
During the project implementation, AB “Linas” will integrate an energy efficiency measure – a 1000 kW solar power plant, which will enable energy savings and reduce electricity costs (it is planned that the solar power plant will produce approximately 950.00 MWh per year). The implementation of the project will also contribute to mitigating the impact of climate change in Lithuania, addressing air pollution issues, and reducing dependence on imported energy resources.
The total eligible cost of the project is 667,242.43 Euros.
Funding allocated for the project implementation from the European Union funds is 149,226.67 Euros.
Project start – October 10, 2023.
The end of the project – 2025. October 31